ACTIVE BUILDING PERMITS
PERMIT # |
SCOPE |
B-2018-2107 | VALLCO TOWN CENTER - MASS EXCAVATION AND STRUCTURAL SHORING FOR ZONE A. |
B-2018-2171 | VALLCO TOWN CENTER - FOOTINGS AND FOUNDATIONS FOR PODIUM STRUCTURE / SEQUENCE #1, BLOCKS 1,2,& 4. |
BLD-2021-0433 | VALLCO TOWN CENTER - SHORING AND MASS EXCAVATION FOR ZONE B1. |
See all Building Permit applications |
CURRENT STATUS UPDATES: (AS OF MAY, 2023)
- Demolition work west of Wolfe Road is complete.
- Mass Excavation and Shoring permits have been issued.
- The review of the Site Management Plan by Santa Clara County, Department of Environmental Health (DEH), is complete and an approval letter has been issued.
- Grading work to excavate and off-haul contaminated soil located on the site west of Wolfe Road commenced on May 22, 2023. This scope includes, but not limited to, the following:
- Excavation and off-haul of impacted soil to appropriate waste disposal facilities
,as approved by DEH; - Real time air monitoring of dust generated by onsite soil removal by environmental professionals;
- Construction activities in accordance with provisions of the City’s Municipal Code, which limit temporary construction work to daytime hours (7:00 AM to 8:00 PM), Monday through Friday (i.e., no work relating to soil removal for this phase will take place on the weekend); and
- No street closures or traffic impacts to any businesses or residences.
This phase of work will be completed by early Summer, at which time utility improvement work will resume and, later in the year, shoring and excavation for the future underground parking facility will commence.
To receive community-wide project updates, interested parties are asked to sign up to a general mailing list at Info@TheRiseCalifornia.com; to receive construction-related updates, interested parties are asked to reach out to the developer at Construction@TheRiseCalifornia.com.
PLEASE CHECK BACK HERE FOR THE LATEST STATUS UPDATES FOR THE RISE PROJECT